Schedule for Week of November 28th, 2011
Dear Tenants,
Pete and I had several “reality check” moments this week. We have since made modifications to the schedule to try to restore the building common areas to their rightful, non-construction-zone, state. Thank you for your patience. (see below post about insurance negotiations for an explanation of the delay).
We need one more week of patience as we work to restore the restrooms and corridors and get the construction guys and their messes out of your way!
Be Prepared for One more Week:
Monday and Tuesday- we will be working in the upstairs restroom drywalling, painting and installing the necessary electrical so it is fully functional, clean and available for use by mid-week.
Wednesday – Friday- we will be working in the downstairs Rudy’s restroom and adjacent corridor to make sure it is fully functional, clean and available for use by the following monday.
We will post directional signage in the building letting clients and customers know when there is a closure of the restroom and where to find alternate facilities (up or downstairs).
Throughout the week we will be trying to improve workman traffic, messes, and impacts on the hallways. By the end of the week I hope to have restored a restroom on each floor and made the hallways as good as new. We will then begin to isolate work in specific areas and provide notice as fewquently as possible of any impacts.
Thanks so much for bearing with us. Please do not hesitate to call us with any concerns about noise, messes or any outages.
Have a great holiday weekend. See you monday!